Main lessons from this article

  • Justify every expense from zero: Zero‑Based Budgeting requires that each expense be explained based on current needs, without automatically inheriting the previous budget. This increases the accuracy of financial planning.

  • Treat electricity as a management lever: for Group A companies, electricity represents one of the main opportunities for applying ZBB, as it allows demand, consumption and charges to be analyzed separately and strategically.

  • Follow a five‑step process: mapping, decision packages, prioritization, consolidation and monitoring form a flow that expands cost visibility and facilitates the reallocation of resources to higher‑value areas.

  • Reduce typical errors with data and sponsorship: avoiding historical anchoring and manager resistance requires leadership support and the use of real hourly measurement data, especially for electricity.

  • Convert savings into renewable energy contracts: companies that apply ZBB can direct part of the savings to renewable energy contracts with predictable pricing. Serena Energia supports the structuring of the electricity decision‑package for the next cycle.

Prerequisites to start ZBB

Gathering four basic conditions prepares the company for a consistent ZBB cycle.

The first step is to have a minimum understanding of the cost structure. The finance team needs to access the income statement (DRE) of the last 12 months, electricity bills with demand and consumption breakdowns, and recurring service contracts. For Group A companies, hourly electricity measurement is an operational requirement that also feeds the decision‑package analysis with real data.

This knowledge allows identification of who is responsible for each spending area. Therefore, the second step is to define the owners of decision packages. Each area—such as operations, IT, marketing and facilities—designates a responsible person who will justify its costs before the budgeting committee. Without this mapping, the process tends to remain confined to the finance team, with low adoption from the areas.

These owners need support to propose changes to historical costs. The third step is to obtain sponsorship from senior leadership. ZBB questions consolidated decisions and can generate resistance. Explicit backing from the CEO or the Board distinguishes a consistent implementation from a project that is halted midway.

All decision packages must be recorded in a single environment. The fourth step is to define a consolidation tool. Advanced spreadsheets or planning modules in ERPs such as SAP or TOTVS meet the needs of most mid‑size companies. The important thing is to record all packages in one place, which enables comparison and prioritization.

Overview of the five‑step process

With these prerequisites met, the company is ready to start the structured ZBB implementation process.

The ZBB process is organized into five sequential steps, each with a clear deliverable that feeds the next.

Step 1 is cost mapping and segmentation, which identifies all decision units and classifies spending by nature and criticality. Step 2 is the construction of decision packages, where each area owner describes what they do, how much it costs and the impact of not doing it. Step 3 is analysis and prioritization, where the budgeting committee ranks the packages by delivered value and strategic alignment. Step 4 is consolidation and approval, where the approved budget is integrated into the projected income statement and communicated to the areas. Step 5 is continuous monitoring, with monthly reviews that compare actuals to approved figures and feed adjustments into the next cycle.

These steps form a cycle. Learnings from monitoring feed back into the mapping of the next cycle and make the process more accurate each round.

Understand, with the Serena Energia team, how to structure the electricity decision‑package so that the free electricity market works as a cost‑reduction lever with long‑term predictability.

Step‑by‑step: how to implement Zero‑Based Budgeting

Step 1 — Cost mapping and segmentation (weeks 1–2)

Goal: create a complete inventory of all operational expenses, grouped by decision unit.

Actions: pull the income statement of the last 12 months, which will serve as the basis for classification. Then, classify each cost line as essential (operation stops without it), relevant (impacts efficiency) or discretionary (can be eliminated or reduced without operational impact). This classification allows identification of which areas control which spend. Therefore, the third action is to map decision units, which are each cost centre or area that controls its own budget.

Attention to electricity: the electricity bill of a Group A company contains distinct components, such as contracted demand, peak‑hour consumption and off‑peak consumption, and sectoral charges. Each component must be mapped separately, as each can generate a different decision package.

Aerial view of a vast solar plant with long rows of photovoltaic panels capturing the sunset light.
Using large‑scale solar farms allows capturing energy with maximum efficiency, optimizing credits that drastically reduce the fixed costs of partner companies.

Risks: under‑estimating the number of decision units creates rework in later steps. The recommendation is to validate the mapping with each area’s managers before moving forward.

Step 2 — Construction of decision packages (weeks 3–5)

Goal: have each area owner describe in writing what its unit does, how much it costs at different service levels, and the impact of each level on the business.

Structure of an electricity decision package:

Element

Description

Package name

Electricity management, Industrial Unit X

Owner

Facilities Manager

Minimum level

Maintain current contracted demand, no review, cost: R$ X/month

Intermediate level

Review contracted demand and migrate to the free electricity market, projected cost: R$ Y/month

Enhanced level

Intermediate level with hourly monitoring and peak adjustment, projected cost: R$ Z/month

Impact of not approving

Maintenance of current cost without long‑term predictability

The same model applies to maintenance packages, with a minimum level based on corrective maintenance and an enhanced level with predictive maintenance under contract. In IT, the minimum level focuses on reactive support and the enhanced level includes proactive monitoring. In marketing, the minimum level covers basic digital presence and the enhanced level includes performance campaigns with demand‑generation targets.

Step 2 validation checklist:

  • Owner defined: each package has an identified responsible.

  • Three clear levels: the three service levels are described with cost and impact.

  • Real electricity data: electricity consumption data uses actual measurements, preferably hourly.

  • Financial review: the finance team reviewed the packages before sending them to the committee.

Receive an analysis of your company’s electricity consumption profile from Serena Energia and identify which service level makes the most sense for the electricity decision package.

Step 3 — Analysis and prioritization (weeks 6–7)

Goal: have the budgeting committee, composed of the CFO, controllers and area representatives, rank all decision packages by delivered value and alignment with the company’s strategic priorities.

Actions: consolidate all packages into a single spreadsheet or planning tool, apply prioritization criteria such as impact on results, operational risk of not approving, and alignment with sustainability goals, and define the approved service level for each package within the available budget envelope.

The table below highlights the main differences between ZBB and traditional budgeting and shows why ZBB expands visibility and cost‑reduction potential.

Comparison between ZBB and traditional budgeting:

Criterion

Traditional budgeting

Zero‑Based Budgeting

Starting point

Previous year’s budget

Zero, each expense is justified from scratch

Cost visibility

Partial, inherits history without questioning

Total, every line is reviewed

Cycle time

Shorter, incremental adjustment

Longer, zero‑based justification in the first rollout

Cost‑reduction potential

Limited to marginal tweaks

Bain & Company clients report 8 %–12 % procurement cost reductions through procurement services

Area engagement

Low, process centralized in finance

High, package owners are responsá

veis pela justificativa

Step 4 — Consolidation and Approval (weeks 8–9)

Objective: integrate the approved packages into the projected P&L and communicate the final budget to the areas.

Actions: consolidate the approved packages by service level in the P&L, generate the monthly budget by cost center, document the decisions in a prioritization meeting minutes, which serves as evidence for audits and board presentations, and communicate to the areas the approved and non‑approved packages, with justification.

Note: electricity packages approved at the intermediate or enhanced level, which include migration to the free energy market, must have the implementation schedule aligned with the migration process, which can take up to six months. Early planning increases the chance that the projected savings materialize within the budgeting year.

Step 5 — Continuous Monitoring (starting week 10)

Objective: compare monthly actuals with approved amounts and trigger revisions when necessary.

Actions: generate monthly variance reports by decision package, hold review meetings with package owners who show deviations above the limit set by the committee, and record learnings to feed the next OBZ cycle.

Common Mistakes and How to Fix Them

Frequent Errors

Disguised historical anchoring: package owners describe three service levels but derive the costs of all levels from history, without questioning the necessity of each expense. The result is an OBZ that looks rigorous but reproduces incremental budgeting.

Manager resistance: areas that see OBZ as a threat to the budget tend to inflate minimum‑level costs to protect the current level. Without leadership sponsorship and clear prioritization criteria, this behavior tends to persist.

Ignored energy seasonality: Group A companies with industrial operations have consumption profiles that vary throughout the year. Energy decision packages built on an atypical month generate inaccurate projections.

Lack of post‑approval review: approving the budget and not monitoring actuals reduces the main benefit of OBZ, which is continuous visibility over resource allocation.

How to Fix

To reduce historical anchoring, the committee must require that the minimum level of each package be built from the question “what is strictly necessary to keep the operation running?” rather than “how much did we spend at minimum last year?”.

To address manager resistance, the company can run training workshops before the process starts and clearly communicate the prioritization criteria. This reduces the perception of threat and increases adoption.

To handle energy seasonality, the recommendation is to use hourly measurement data from the last 12 months to build a monthly load curve. This data serves as the basis for an energy decision package that reflects the company’s operational reality.

To avoid lack of review, the company can institutionalize a monthly variance meeting with a fixed agenda and participation of package owners with relevant deviations.

Validation checklist by step:

  • Step 1: the cost inventory covers 100 % of the P&L.

  • Step 2: all packages have three levels with documented cost and impact.

  • Step 3: prioritization criteria were applied consistently to all packages.

  • Step 4: the projected P&L exactly reflects the approved packages.

  • Step 5: variance reports are being generated and reviewed monthly.

How to Verify the Results?

A well‑executed OBZ results in a projected P&L where each line is linked to an approved decision package. This document, accompanied by the prioritization meeting minutes, composes the material that the controller presents to the board as evidence of rigor in budget construction.

Key process indicators include the package approval rate by service level, which shows whether the committee is prioritizing with criteria or approving everything at the maximum level; the reduction of variance between budgeted and actual over cycles, indicating the use of more accurate data; and the OBZ cycle time, which shows efficiency gains each round.

The recommended review cadence is monthly for cost variance and quarterly for reviewing packages that show a relevant change in the operational context, such as a shift in energy consumption profile after migrating to the free energy market.

The most used tools by medium‑ and large‑size Brazilian companies include planning modules in ERPs, such as SAP BPC and TOTVS Planning, and advanced spreadsheets with version control. The central point is that the environment allows tracing each P&L line back to the decision package that originated it.

Advanced Options and Related Topics

Companies with multiple consumption units, such as industrial plants, distribution centers, and offices, can apply OBZ in a consolidated manner, with decision packages per unit and a corporate prioritization layer. This model facilitates comparison between units and shows which operations have proportionally higher energy costs and where migration to the free energy market generates the greatest impact.

Integration with ERPs allows loading the approved packages directly as budgeted cost centers. This eliminates re‑typing work and reduces the risk of inconsistencies between the approved budget and the control system.

For companies with sustainability goals, OBZ creates space to treat the renewable energy decision package as a strategic priority, not just a cost line. Long‑term contracts in the free energy market with 100 % renewable supply and issuance of Renewable Energy Certificates (I‑RECs) enter as an investment with measurable return in Scope 2 emissions reduction.

Landscape of a renewable energy park at sunset, showing large wind turbines and vast rows of solar panels over hills.
The strategic combination of wind and solar sources maximizes clean energy generation, ensuring greater stability and efficiency for Free Market supply.

The OBZ is also recognized as an effective tool to respond to cost shocks, including fluctuations in energy and commodities, because it creates visibility over discretionary spending and allows targeted resource reallocation. When a company combines OBZ with a free‑energy‑market contract with a pre‑defined price, the finance team gains visibility and predictability to plan with greater confidence.

Frequently Asked Questions

Does my Group A company need a minimum consumption to apply OBZ to electricity?

There is no minimum consumption to apply OBZ. The methodology adapts to any Group A company, which are companies with medium or high‑voltage supply, regardless of the amount of energy consumed. The complexity of the bill, not the size of consumption, defines the depth of the energy decision package.

How long does OBZ implementation take in a medium‑size Brazilian company?

The full cycle, from mapping to budget approval, usually takes a few months and requires greater effort in the first implementation. In subsequent cycles, with package owners already trained and historical data organized, the process tends to become faster.

Who should be responsible for the electricity decision package?

The owner of the electricity decision package is typically the Facilities Manager or the Operations Manager, who control the consumption profile and contracted demand. The Controller or the CFO acts as reviewer and integrator of the package into the projected P&L. In companies with multiple units, there may be an owner per consuming unit and a corporate consolidator.

Is there a risk of accidentally cutting an essential package during OBZ?

This risk exists, but the three‑level service structure reduces the possibility. The minimum level of each package describes what is strictly necessary to keep the operation running. If the committee approves only the minimum level of an essential package, the operation continues, with reduced comfort or efficiency but without interruption. Cuts below the minimum level represent a conscious decision, not a process error.

How does the free energy market fit into OBZ for a Group A company?

Migrating to the free energy market appears as the intermediate or enhanced level of the electricity decision package. At the intermediate level, the company maintains current consumption and negotiates price with a supplier of its choice, such as Serena Energia, instead of paying the regulated tariff. The result is an energy cost with a pre‑defined price, eliminating tariff‑flag fluctuations and increasing the accuracy of meeting the approved budget throughout the year. Serena Energia offers long‑term contracts with 100 % renewable supply and I‑REC issuance, linking OBZ cost‑reduction goals to the company’s sustainability targets.

A single white wind turbine stands out amid a dense layer of fog or clouds, illuminated by the soft light of sunset.
Advanced wind technology enables Serena Energia to capture steady winds at high altitudes, providing a clean, stable, and efficient energy source for your business.

Request an analysis of your consumption profile with Serena Energia to structure the electricity decision package for the next OBZ cycle.

Conclusion

By completing the five steps of this guide, the finance team of a Group A company gains a budget that provides visibility over every cost line, documented and prioritized decision packages, and a projected P&L that the board can audit line by line. Electricity, often treated as an inevitable fixed cost, becomes an active decision, with service levels, responsible owners, and concrete reduction alternatives.

Serena Energia, among the largest wind and solar generators in the Americas, offers long‑term contracts in the free energy market with 100 % renewable supply, I‑REC certification, and simplified management for Group A companies across Brazil. These contracts turn electricity into a more predictable budget line, aligned with the discipline that OBZ demands.

Contact us

with Serena Energy and direct your company's energy towards business growth.

Redação Serena Energia

André Lima

We are part of Serena, one of the country's leading generators and traders of clean energy, with 15 years of experience connecting people and businesses to sustainable and competitive solutions. Here on the blog, you'll find content on the electricity sector, Free Energy Market, sustainability, and energy transition, with clear explanations to support decisions in your daily life, whether at home or in your business.

Editor

Leave a comment

Your email address will not be published. Required fields are marked with *