How to scale with operational efficiency: guide for Group A

Written by: André Lima, Growth, Serena Energia
Key lessons from this article
- Scaling operations efficiently requires treating energy cost as a strategic and predictable variable, especially for Group A companies connected to medium and high voltage.
- Conducting a complete diagnosis of the consumption profile for the last 12 months allows identifying inefficiencies and renegotiating contracted demand before migrating to the free energy market.
- Running the migration process to the free energy market in five macro steps takes about six months, making it essential to start early to capture benefits sooner.
- Involving finance, operations, legal and ESG areas from the start, as well as a specialized manager, reduces risks and keeps the operation impact‑free.
- With Serena Energia, Group A companies can start a cost‑free feasibility study and treat energy cost as a competitive advantage; talk to one of our consultants.
Prerequisites to start the journey
Starting the migration to the free energy market or an operational efficiency restructuring requires internal organization and clear responsibility definition.
The areas that must be involved from the beginning are:
- Finance and controlling: for impact analysis on the P&L and contractual approval
- Operations and facilities: to map the consumption profile by unit and shift
- Legal: to review contracts with the current distributor and the new supplier
- ESG or sustainability, when applicable: to align with emission targets
Gathering complete documents and data speeds up the process and reduces rework.
- Energy invoices from the last 12 months for all consumer units
- Contracted demand compared with measured demand per unit
- Monthly consumption profile in kWh, with seasonality and identified peaks
- Current tariff modality, green or blue, and voltage group
- Corporate structure, with root CNPJ, to assess contractual unification in scenarios with multiple units
From a technical standpoint, the company must be connected to medium or high voltage to be eligible for the free energy market. There is no minimum consumption required; it only needs to belong to Group A. Serena Energia performs the eligibility analysis at no cost.
Overview of the process in 5 macro steps
With prerequisites mapped, areas involved and documentation organized, the company is ready to start the migration journey.
When a specialized manager leads the process, migration to the free energy market follows five linked phases, from the initial diagnosis to continuous post‑migration management.
- Feasibility study: analysis of invoices and consumption profile to project savings and validate eligibility
- Contract closing: definition of price, term—typically five years—and conditions with the chosen retailer
- Migration management: handling the bureaucratic process with the distributor and the CCEE (Electric Energy Commercialization Chamber), including measurement system adaptation
- Go‑live: effective entry into the free energy market, with the start of contracted savings
- Continuous management: performance monitoring, representation before the Chamber and dedicated consulting support
Each phase depends on the previous one. The time between the start of the process and go‑live is six months, determined by the notice period required to terminate the contract with the distributor. Therefore, starting the process early allows capturing results sooner.
Talk to one of our consultants to start a cost‑free feasibility study for your company.
Step‑by‑step guide
Step 1: map the consumption profile and identify inefficiencies
The starting point is an analysis of the invoices from the last 12 months. The goal is to compare contracted and measured demand, identify consumption peaks, verify the tariff modality and detect power‑factor charges below the regulatory minimum. For Group A companies, this analysis can reveal contracted demand significantly higher than measured demand, allowing renegotiation of the fixed component of the bill without infrastructure investment.
The controller or facilities manager should lead this analysis, as they have access to the invoices of all units, which are the basis for a reliable diagnosis. The main risk is working with incomplete invoices or atypical periods, which distorts the diagnosis and compromises savings projections.
Step 2: request a feasibility study from a retailer
With the consumption profile mapped, the company requests a feasibility study from an energy retailer. Serena Energia, one of the largest wind and solar generators in the Americas with over 17 years of history, conducts this study at no cost and projects the expected savings based on the company's real data.

The CFO or controller is usually the internal owner of this step, as they validate assumptions and budget impacts. This phase depends on the consolidated data from the previous step. The key attention point is to compare projection methodologies among suppliers and prioritize conservative, auditable assumptions.
Talk to one of our consultants and receive your company's feasibility study.
Step 3: close the energy contract
After validating the study, the company signs the contract with the chosen retailer. In the retail model, recommended for most Group A companies, the client does not purchase a specific volume of energy but defines the price to be paid. At the end of each month, the invoice is calculated by multiplying that price by the actual consumption. Long‑term contracts lock the price in advance and eliminate the uncertainty of tariff flags.
The legal and financial areas must conduct this step together. Contract signing depends on internal approval of term and conditions. The main risk is not involving the legal team in reviewing flexibility and termination clauses.
Step 4: start the managed migration process
In this stage, Serena Energia takes charge of the migration process, at no additional cost to the client. Activities include notifying the distributor, registering with the CCEE (Electric Energy Commercialization Chamber) and preparing the required technical, legal and financial documentation. The standard timeline is six months from notification.
The facilities or operations area acts as the internal responsible, providing technical access when needed. This phase depends on the signed contract. Delays in delivering internal documentation can jeopardize the schedule.
Step 5: adapt the measurement system
Hourly measurement is mandatory in the free energy market. Serena Energia is responsible for installing compatible measurement equipment, with this service included in the migration process. This step occurs within the migration period and does not impact operations.
The plant or facilities manager coordinates physical access to the measurement points. The local distributor’s schedule guides execution. The key attention point is to confirm in advance the availability of access to the measurement point.
Step 6: go‑live and initial monitoring
After six months, the company enters the free energy market and begins receiving two invoices: an energy invoice issued by Serena Energia and a distribution invoice issued by the local distributor, which remains responsible for the physical delivery of electricity. Serena Energia centralizes management and provides a digital dashboard with monthly savings, actual consumption, consumption forecast and a comparison between captive and free energy markets.

The controller and facilities area usually monitor this phase. The completion of go‑live is the main dependency. The key attention point is to verify in the first invoice that the amounts match the projections from the feasibility study.
Step 7: establish operational and energy efficiency KPIs
With energy cost predictability established, the company can integrate energy indicators into the operational efficiency dashboard. Recommended KPIs include energy cost per produced unit, consumption in kWh per shift or line, and accumulated savings compared with the captive market. These data support capacity expansion decisions without proportional cost increases.
The controller and operations director lead this step, using data from the Serena Energia dashboard integrated into the ERP or management system. Quarterly KPI reviews help identify deviations and adjustment opportunities.
Common mistakes and how to avoid them
Planning
Starting the process without a complete consumption‑profile diagnosis reduces the potential for savings. Companies that do not analyze the previous 12 months of invoices miss the chance to renegotiate contracted demand before migration, diminishing the total benefit.
Timelines
Underestimating the six‑month timeline is a recurring error. Companies that wait for the current contract to expire before starting lose months of savings. Planning should begin early enough for migration to occur at the desired strategic moment.
Documentation
Delays in delivering technical and legal documentation are the main cause of extended migration timelines. Creating an internal checklist with all required documents and assigning a single owner for collection and submission reduces this risk.
Alignment between areas
Migrating to the free energy market without involving legal and finance from the start generates rework in contract review and can delay internal approvals. The four areas—finance, operations, legal and ESG—should be mobilized simultaneously from step 1.
Result verification and metrics
The confirmation that the migration was executed correctly appears
in the first invoices and in the monitoring dashboard. The recommended indicators are:
- Financial: monthly savings in reais compared to the feasibility study projection, energy cost per unit produced, cumulative savings since go-live
- Operational: actual consumption compared to the consumption forecast, absence of charges for contracted demand above the measurement, power factor compliance
- Sustainability: MWh consumed from certified renewable source, I-RECs issued for ESG reporting
The review of these indicators should occur monthly during the first six months post-go-live and quarterly from the seventh month onward. Serena Energia's digital dashboard centralizes this data and allows direct comparison of the cost in the regulated market with the current cost in the free energy market.
Broader operational efficiency can be monitored through indicators such as OEE (Overall Equipment Effectiveness), calculated as availability × performance × quality, and cost per unit produced. With predictable and fixed energy cost, variations in these indicators more accurately reflect the real efficiency of production processes, without the noise of tariff fluctuations.
Talk to one of our consultants to structure the monitoring dashboard appropriate for your company's profile.
Advanced options and next steps
Companies with multiple consumer units can unify energy management under a single contract or portfolio in the free energy market, regardless of the local distributor of each unit. This model enables centralized negotiation and consolidated monitoring, reducing administrative complexity. Contractual unification can occur by legal affiliation, with the same root CNPJ, or by factual affiliation, in contiguous units.
For companies with public sustainability targets, contracting renewable energy in the free market enables the issuance of I-RECs, international certificates that audibly prove that each MWh consumed originates from a clean source. Serena Energia provides these certificates and also offers carbon credits to offset emissions from other scopes, completing the company's ESG strategy.

Related topics for deeper study include energy management in multi‑unit operations, industrial decarbonization strategies, and integration of energy data into ERP systems.
Frequently Asked Questions
Does my company need a minimum consumption to migrate to the free energy market?
No. Any company connected at medium or high voltage, i.e., belonging to Group A, can migrate to the free energy market, regardless of consumption volume. The analysis mentioned earlier confirms your company's eligibility at no cost.
How long does the migration process take?
The timeline is six months from notification to the current distributor. During this period, Serena Energia conducts the process steps, such as documentation, registration with CCEE (Electric Energy Commercialization Chamber), and measurement system adaptation, at no additional cost to the client. Therefore, starting the process early is essential to anticipate the benefits.
Can the migration cause an interruption in energy supply?
No. Migration is a commercial and contractual process. The local distributor remains responsible for the physical delivery of electricity and network quality. The only change is the energy supplier. Operations are not impacted during or after migration.
Which internal areas need to be involved in the process?
The finance, operations or facilities, legal, and, when applicable, ESG areas should be mobilized from the start. Finance validates the impact on the P&L and approves the contract. Operations and facilities provide consumption data and enable technical access for installing measurement equipment. Legal reviews the contractual clauses. Serena Energia offers specialized support to all these fronts throughout the process.
What happens if my company consumes more or less energy than contracted?
In the retail model of the free energy market, the client sets the price they will pay for energy, and the monthly invoice is calculated by multiplying that price by the actual consumption. There is no penalty for consumption variation in this model. Serena Energia provides a dedicated consultant and a monitoring dashboard to track consumption and anticipate adjustments when needed.
Conclusion
Scaling with operational efficiency requires that the main cost drivers be predictable and controllable. For Group A companies, which consume at medium and high voltage, treating energy as a strategic variable rather than a residual expense has a significant impact on financial planning and the ability to grow without a proportional cost increase.
The roadmap presented in this guide, from consumption diagnosis to continuous post‑migration monitoring, offers CFOs, controllers, and operations managers a structured, low‑risk path to reduce tariff uncertainty in budgeting and free up resources for strategic investments.
Serena Energia conducts this process in a managed way and at no additional cost to the client, from the feasibility study to continuous post‑go‑live management.
Talk to one of our consultants and take the first step to treat energy cost as a competitive advantage.

André Lima
We are part of Serena, one of the country's leading generators and traders of clean energy, with 15 years of experience connecting people and businesses to sustainable and competitive solutions. Here on the blog, you'll find content on the electricity sector, Free Energy Market, sustainability, and energy transition, with clear explanations to support decisions in your daily life, whether at home or in your business.
Editor
Leave a comment
Your email address will not be published. Required fields are marked with *