Key takeaways from this article

  • Companies in Group A, operating at medium or high voltage, do not benefit from the shared energy cooperative model, which primarily serves consumers in Group B.

  • The free energy market offers contracts with fixed prices for 3 to 5 years, greater predictability, and complete management at no additional cost to the customer.

  • The migration to the free energy market follows a 6-month regulatory process, which includes notification to the distributor, registration with the CCEE (Chamber of Electric Energy Commercialization), and adaptation of the metering system.

  • In addition to allowing savings of up to 20% on electricity bills, the free energy market enables the issuance of I-RECs (Renewable Energy Certificates) to prove renewable energy consumption in sustainability reports.

  • To begin the migration safely and obtain a personalized feasibility study, speak with Serena Energia .

Prerequisites: what your company needs to have before making any decisions.

Confirming the company's tariff group is the first step in evaluating any energy discount model. Group A includes consumers served at medium voltage, from 2.3 kV to 44 kV, and high voltage, above 69 kV. Since January 2024, any company in Group A can migrate to the free energy market, regardless of consumption volume.

To begin the analysis, gather the following documents and information:

  • Energy bills from the last 12 months

  • Supply voltage level, identified on the invoice itself.

  • Current contracted demand

  • Monthly consumption profile in kWh, including seasonal variations and peaks.

  • Taxpayer Identification Number (CNPJ) and technical documentation of the consumer unit.

With this information, the company can conduct a feasibility study that projects the real savings in the free energy market. Serena Energia performs this analysis free of charge for eligible companies.

Overview of the 5-step process

These five steps organize the transition from initial diagnosis to follow-up of results. The prerequisites allow for safe progress through each phase.

  1. Check eligibility and consumption profile.

  2. Analyzing the cooperative model versus the free energy market.

  3. Choose a partner and sign the energy supply contract.

  4. Execute the migration, within a 6-month regulatory process.

  5. Monitor the economy and renewable energy certifications.

Step-by-step guide: how to migrate to the free energy market

The following guide details these five steps and shows how each decision prepares the way for the next step, leading to savings on your bill.

Step 1 — Verify eligibility and consumption profile

Objective: to confirm that the company is in Group A and to map its consumption pattern.

Actions: Identify the voltage level on the bill to confirm classification in Group A. With eligibility confirmed, gather the consumption history for the last 12 months and map seasonal patterns, as this data feeds into the feasibility study. If the company operates multiple consumer units, check if they can all be included in the same energy supply contract, which consolidates the volume and can increase savings.

Responsible parties: facilities manager, controller, or internal energy manager, with support from the chosen energy trading company.

Risks and points of attention: companies that are not in Group A are not eligible for the free energy market. Low-voltage units may have alternatives via shared renewable energy, in a model distinct from the free energy market.

Step 2 — Analyze the cooperative model versus the free energy market.

Objective: to understand the structural differences between the two models and choose the one most suitable for the company's profile.

Actions: compare price predictability, contract term, management responsibility, renewable certification, and typical savings. The table below shows that the free energy market offers superior predictability in criteria that impact the financial planning of Group A companies.

Criterion

Shared energy cooperative (Group B)

Free energy market with Serena Energia (Group A)

Target audience

Low-voltage consumers, Group B

Medium and high voltage companies, Group A

Price predictability

Variable, depends on credits generated and processed by the distributor.

Fixed price in a bilateral contract of 3 to 5 years.

Contract term

Variable by cooperative, loans valid for up to 60 months.

Contracts typically for 5 years.

Management and bureaucracy

Dependence on the local distributor for credit processing, with operational bottlenecks reported in 2026.

Complete management by Serena Energia, at no additional cost to clients under its management.

Renewable certification

No I-RECs issued to the consumer.

I-RECs issued per MWh consumed, valid for ESG reports.

Typical economy

Between 10% and 20% for Group B consumers in 2026.

Up to 20% compared to the regulated market, according to data from Serena Energia.

Responsible parties: Chief Financial Officer, Controller, and ESG Manager.

Risks and points of attention: In March 2026, the cooperative reported critical dependence on distributors and technological lag as barriers to the scalability of the shared model. Delays in credit processing reduce financial predictability and confidence in the cooperative model. For Group A companies, these risks cease to exist in the free energy market because the price is fixed by contract before the start of supply.

Request a customized comparative study to understand which model delivers more predictability for your company.

Step 3 — Choose a partner and sign the energy supply contract.

Objective: to select a trading company with its own generation capacity, financial stability, and full management capabilities.

Actions: Assess whether the company has its own generation or only resells energy from third parties, because generators with their own assets offer greater security of supply. Confirm market experience, customer portfolio, and representation model at CCEE (Chamber of Electric Energy Commercialization), which are indicators of operational solidity. Verify if the migration is managed without additional cost, which reduces barriers to entry. With these criteria validated, sign the bilateral energy supply contract with a fixed price.

Responsible parties: financial director, legal director, and operations manager.

Risks and points of attention: energy trading companies without their own generation depend on buying energy from third parties, which can represent a greater supply risk. Serena Energia is one of the largest wind and solar energy generators created in the Americas, with more than 17 years of history, 17 operational plants and clients such as Heineken, Cargill, Eurofarma and Bayer. This integration between generation and trading reduces the risk for the client.

Silhouette of several wind turbines lined up along the coast during a colorful sunset, with reflections in the water.

The exploitation of natural resources, such as coastal winds, is essential to maintain the scale and sustainability needed in the Free Energy Market.

Learn about Serena Energia's contractual terms and see how vertical integration reduces supply risk.

Step 4 — Execute the migration, within 6 months.

Objective: To complete all regulatory and technical steps to begin supplying energy in the free market.

Actions: Serena Energia manages the entire process for clients under its control, at no additional cost. The flow follows this sequence:

  1. Months 1–2: notification to the local distributor, termination of the current contract, and commencement of the registration process with CCEE (Chamber of Electric Energy Commercialization).

  2. Months 3–4: Submission of technical, legal, and financial documentation; adaptation of the metering system (SMF); and installation of metering equipment by Serena Energia, at no cost to the client.

  3. Months 5–6: validation of registration with CCEE (Chamber of Electric Energy Commercialization), hourly metering tests, and completion of migration.

  4. Month 6: Start of supply in the free energy market and issuance of the first bill with savings.

Responsibilities: Serena Energia handles all stages, and the client provides documentation and access to the metering system.

Risks and points of attention: the 6-month deadline is regulatory and cannot be reduced. The sooner the company starts the process, the sooner it begins to save money. The local distributor remains responsible for the physical delivery of energy during and after the migration. What changes is only from whom the company buys the energy.

Step 5 — Monitor savings and renewable energy certifications

Objective: to monitor the financial and environmental results of the energy supply contract.

Actions: Access the Serena Energia dashboard to track, in a single environment, your monthly savings on your bill, total consolidated savings, comparison between the regulated and free energy markets, consumption forecasts, and actual consumption. Request the issuance of I-RECs for sustainability reports.

A single white wind turbine stands out amidst a dense layer of mist or clouds, illuminated by the soft light of the setting sun.

Advanced wind technology allows Serena Energia to capture consistent winds at high altitudes, ensuring a clean, stable, and efficient energy source for your business.

Responsible parties: controller, ESG manager, and dedicated consultant at Serena Energia.

Risks and points of attention: contracts in the retail model provide for consumption flexibility generally between 5% and 10% of the contracted volume. Consumption outside this range is settled in the short-term market. Serena Energia offers active management to reduce this exposure.

Common mistakes and how to correct them.

  • Confusing Group A with Group B: check the voltage level on your bill before making any decisions. Cooperatives primarily serve Group B customers, while Group A companies have access to the free energy market.

  • Ignoring the 6-month timeframe: savings only begin with the first bill after the migration is complete. Planning ahead avoids frustration from expecting quick results.

  • Expecting fixed savings without a contract: in the cooperative model, credits depend on processing by the distributor and may vary. In the free energy market, the price is fixed in a contract before the start of supply.

  • Choosing a supplier without its own generation: companies that only resell energy from third parties have less supply backing. Prioritizing generators with their own assets reduces operational risk.

  • Failing to map consumption profiles before signing a contract: seasonality and demand peaks influence the contract design. A poorly sized contract can lead to short-term market exposure.

  • Underestimating the importance of renewable certification: I-RECs are required by investors, clients, and sustainability reports. Contracts without certification of origin do not meet Scope 2 targets.

How to verify the results and measure the real savings.

The correct comparison considers the effective cost per kWh in the regulated market, which includes energy, TUSD (Transmission System Usage Tariff), charges, tariff flags, and taxes, and the cost in the free energy market, where the energy portion is fixed in the contract and tariff flags do not apply to that portion.

Serena Energia's dashboard brings together, in one place, the main indicators to monitor the contract's performance:

  • Savings on your current month's bill.

  • Economic stability since the beginning of the contract.

  • Detailed billing breakdown with a comparison between the regulated and free energy markets.

  • Consumption forecast for the following month

  • Consumption carried out up to the date of the query.

For the ESG area, the panel also records the I-RECs issued, which prove the renewable origin of each MWh consumed and are used directly in sustainability reports for offsetting Scope 2 emissions. Since 2017, Serena Energia has avoided the emission of more than 2.14 million tons of CO₂.

Landscape of a renewable energy park at sunset, featuring large wind turbines and vast rows of solar panels on hills.

The strategic combination of wind and solar sources maximizes clean energy generation, ensuring greater stability and efficiency for the supply of the Free Market.

Advanced options and next steps

Companies already operating in the retail model of the free energy market can, as they grow in consumption and management capacity, evaluate migrating to the wholesale model. In this model, the company acts directly as an agent in the CCEE (Chamber of Electric Energy Commercialization), managing its own risks and contracts, with greater flexibility and control over purchasing conditions.

Other possible evolutions include:

  • Addition of I-RECs to the contract for full coverage of Scope 2 emissions.

  • Acquisition of carbon credits for offsetting Scope 1 and 3 emissions.

  • Early contract renewal to maintain price predictability for another 3 to 5 years.

  • Inclusion of new consumer units in the same energy supply contract.

Frequently Asked Questions

How does the cooperative work and who is it suitable for?

The cooperative is a shared renewable energy cooperative that distributes energy credits generated at partner plants among its members, offsetting these credits against electricity bills. The model primarily serves Group B consumers, such as residences, small businesses, and low-voltage companies. For Group A companies, connected to medium or high voltage, the cooperative model does not offer the same predictability or the same contractual conditions available in the free energy market.

Is a cooperative worthwhile for companies in Group A?

For Group A companies, the cooperative model presents significant structural limitations. Energy credits depend on processing by the local distributor, and technological and operational delays in this process reduce financial predictability. Furthermore, the cooperative model does not offer long-term fixed-price contracts or the issuance of I-RECs for sustainability reporting. The free energy market, with bilateral contracts of 3 to 5 years and complete management by a generator like Serena Energia, delivers greater predictability and more tools for financial and ESG management.

How does canceling or leaving an energy cooperative work?

Exit conditions vary according to each cooperative's bylaws. Generally, contracts define notice periods, credit transfer conditions, and any potential penalties. Shared renewable energy credits are valid for up to 60 months and can be transferred after the contract ends, according to the distributor's rules. Before joining any model, it's worth carefully reviewing all exit clauses.

What is the difference between an energy cooperative and a free energy market?

A shared energy cooperative is a credit compensation model for Group B consumers, without a fixed-price contract and dependent on processing by the distributor. The free energy market is a bilateral contracting environment in which Group A companies negotiate directly with generators or traders, fixing price, term, volume, and energy source in a contract. In the free energy market, the local distributor remains responsible for the physical delivery of electricity. What changes is from whom the company buys the energy and at what price.

Do I need to install panels or equipment to migrate to the free energy market?

There is no need to install renewable energy panels. Serena Energia generates energy in its large-scale, high-efficiency wind farms, and the local distributor delivers this energy to the consumer unit. The only equipment required is the metering system, SMF, whose installation is the responsibility of Serena Energia and does not generate additional costs for the customer.

How long does it take to start saving money in the free energy market?

As detailed in the migration section, the regulatory process takes 6 months from notification to the distributor. The savings appear on the first bill after the migration is complete. Serena Energia conducts all stages of this process for clients under its management, at no additional cost.

What are I-RECs and why are they important for businesses?

I-RECs, International Renewable Energy Certificates, are traceable digital certificates that prove that 1 MWh of energy was generated from a renewable source and injected into the grid. For companies with ESG goals, I-RECs are the standard instrument for declaring that electricity consumption is 100% renewable and for offsetting Scope 2 emissions in sustainability reports. Serena Energia issues I-RECs corresponding to each client's consumption.

Side view of a worker at a wind farm, with the sun in the background and several wind turbines stretching to the horizon.

The dedication of qualified professionals in the field is what guarantees the efficiency and constant availability of clean energy that drives our clients' businesses.

In conclusion: the right path depends on your company's tariff group.

Shared energy cooperatives offer a viable alternative for Group B consumers. For Group A companies connected to medium or high voltage, the free energy market delivers greater predictability, fixed-price contracts for 3 to 5 years, complete management at no additional cost, and renewable energy origin certification via I-RECs.

With the operational solidity described above, Serena Energia manages the entire migration process, from eligibility analysis to monthly monitoring of savings, at no additional cost to companies under its management. Savings can reach up to 20% compared to the regulated market, with prices fixed in a contract before the start of supply.

Request a customized feasibility study to assess your company's potential for savings in the free energy market.

Redação Serena Energia

André Lima

We are part of Serena, one of the country's leading generators and traders of clean energy, with 15 years of experience connecting people and businesses to sustainable and competitive solutions. Here on the blog, you'll find content on the electricity sector, Free Energy Market, sustainability, and energy transition, with clear explanations to support decisions in your daily life, whether at home or in your business.

Editor

Leave a comment

Your email address will not be published. Required fields are marked with *